TAP Pipe Deliveries Complete to Albania, Greece and Italy
On 10 October 2017, the last shipment of steel line-pipes for the construction of the Trans Adriatic Pipeline (TAP) arrived in Thessaloniki, Greece, marking the completion and final delivery of all line-pipes to TAP’s host countries.

The transport of 55,000 TAP pipes and bends was completed in approximately one year and a half. The first pipes arrived in Durrës, Albania in April 2016 and deliveries to Greece started one month later, in May 2016.

- Approximately 55,000 pipes are used to build TAP (32,000 in Greece; 13,000 in Albania; 9,150 offshore and 670 in Italy)
- The weight of all pipes amounts to 520,000 tonnes: or approximately 71 Eiffel towers.
- The weight of a single 18-metre pipe ranges from 9.3 tonnes to 16.3 tonnes, depending on the wall thickness.
- The pipes were transported to TAP’s main marshalling yards in 79 sea vessel shipments of various sizes and 158 block trains within Greece. The offloading of the largest ships took five days on average.
- The pipes were manufactured by Corinth Pipeworks (Greece) and Salzgitter Mannesmann International (Germany).

John Haynes, TAP Project Director, noted: “This is yet another key milestone towards successful realisation of the project. The entire logistics delivery process was carried out in line with the project schedule and to the highest safety standards. Considering that each pipe has been lifted approximately seven times from production at the mills until reaching our main marshalling yards, we are proud that this massive operation has been completed without any safety incidents within our host countries. I would like to thank our contractors and sub-contractors responsible for shipping, offloading and transporting TAP pipes for their professionalism, hard work and commitment to safety.”

From the main marshalling yards, the pipes are transported further to the local pipe yards near the construction sites, along the pipeline route.

About the Trans Adriatic Pipeline (TAP)

TAP will transport natural gas from the giant Shah Deniz II field in Azerbaijan to Europe. The 878km long pipeline will connect with the Trans Anatolian Pipeline (TANAP) at the Turkish-Greek border at Kipoi, cross Greece and Albania and the Adriatic Sea, before coming ashore in Southern Italy.

TAP’s routing can facilitate gas supply to several South Eastern European countries, including Bulgaria, Albania, Bosnia and Herzegovina, Montenegro, Croatia and others. TAP’s landfall in Italy provides multiple opportunities for further transport of Caspian natural gas to some of the largest European markets such as Germany, France, the UK, Switzerland and Austria.

TAP will promote the economic development and job creation along the pipeline route; it will be a major source of foreign direct investment and it is not dependent on grants or subsidies. With first gas sales to Georgia and Turkey targeted for late 2018, first deliveries to Europe will follow in 2020.

TAP’s shareholding is comprised of BP (20%), SOCAR (20%), Snam S.p.A. (20%), Fluxys (19%), Enagás (16%) and Axpo (5%).


Origine : Communiqué Trans Adriatic Pipeline

Voir la fiche entreprise de "Trans Adriatic Pipeline"



Les dernières news de "Trans Adriatic Pipeline"



Toutes les news de "Trans Adriatic Pipeline"
 
 
Emploi-Pétrole
 
Rechercher une news



française internationale








 
Les dernières news internationales


>> Toute l'actualité internationale     >> RSS
 



Europétrole © 2003 - 2024