Newsletter 
  INSCRIPTION Inscription | ESPACE ANNONCEURS Publicité | CONTACT Contact |PLAN DU SITE Plan


Europétrole, le portail de l'industrie du pétrole
 
 accueil | actualité française | actualité internationale | recherche | interviews | focus | actualité par entreprise | actualité pétrole/gaz de schiste 
Partager :

  • Santos announces FID on the Barossa gas project for Darwin LNG
    édité le 30/03/2021 - Plus de news de "Santos" - Voir la fiche entreprise de "Santos"


Santos announces FID on the Barossa gas project for Darwin LNG
Santos, as operator of the Barossa joint venture, announced a final investment decision (FID) has been taken to proceed with the US$3.6 billion gas and condensate project, located offshore the Northern Territory.

Barossa FID also kick-starts the US$600 million investment in the Darwin LNG life extension and pipeline tie-in projects, which will extend the facility life for around 20 years. The Santos-operated Darwin LNG plant has the capacity to produce approximately 3.7 million tonnes of LNG per annum.

Barossa is one of the lowest cost, new LNG supply projects in the world and will give Santos and Darwin LNG a competitive advantage in a tightening global LNG market. The project represents the biggest investment in Australia’s oil and gas sector since 2012.

Santos Managing Director and Chief Executive Officer Kevin Gallagher said FID on Barossa was consistent with Santos’ strategy for disciplined growth utilising existing infrastructure around the company’s core assets.

“Our strategy to grow around our five core asset hubs has not changed since 2016. As we enter this next growth phase, we will remain disciplined in managing our major project costs, consistent with our low-cost operating model,” Mr Gallagher said.

“As the economy re-emerges from the COVID-19 lockdowns, these job-creating and sustaining projects are critical for Australia, also unlocking new business opportunities and export income for the nation. The Barossa and Darwin life extension projects are good for the economy and good for local jobs and business opportunities in the Northern Territory.

“Barossa and Darwin LNG life extension will create 600 jobs throughout the construction phase and secure 350 jobs for the next 20 years of production at the Darwin LNG facility.

“Less than a year since we completed the acquisition of ConocoPhillips’ northern Australia and Timor-Leste assets and despite the global economic impact of a once-in-a-hundred-year pandemic, it is a great achievement to have extended the life of Bayu-Undan following the approval of the infill drilling program and now to have taken FID on the Barossa project. I’d like to thank the Australian, Northern Territory and Timor-Leste governments, our joint venture partners and our customers for their support.

“I am delighted to welcome our Barossa joint venture partner SK E&S as a partner in Bayu-Undan and Darwin LNG and appreciate their support for today’s Barossa development decision.”

The Barossa development will comprise a Floating Production, Storage and Offloading (FPSO) vessel, subsea production wells, supporting subsea infrastructure and a gas export pipeline tied into the existing Bayu-Undan to Darwin LNG pipeline. First gas production is targeted for the first half of 2025.

At the end of last year, Santos announced the tolling arrangements had been finalised for Barossa gas to be processed through Darwin LNG and that Santos had signed a long-term LNG sales agreement with Diamond Gas International, a wholly-owned subsidiary of Mitsubishi Corporation, for 1.5 million tonnes of Santos-equity LNG for 10 years with extension options.

Santos has also signed Memoranda of Understanding with SK E&S and Mitsubishi to jointly investigate opportunities for carbon-neutral LNG from Barossa, including collaboration relating to Santos’ Moomba CCS project, bilateral agreements for carbon credits and potential future development of zero-emissions hydrogen.

“We will continue to explore the potential for carbon-neutral LNG from Barossa as part of our commitment to lower global emissions and as a company, reach our net-zero emissions target by 2040,” Mr Gallagher said.

Barossa FID is the final condition required for completion of the 25 per cent equity sell-downs in Darwin LNG and Bayu-Undan to SK E&S, which is also a partner in Barossa. Completion of the SK transaction is expected to occur at the end of April and result in net funds to Santos of approximately US$200 million, being the sale price of US$390 million less the forecast cashflows from the 25 per cent interests from the effective date of 1 October 2019 to completion.

Santos and JERA continue to progress the binding sale and purchase agreement for JERA to acquire a 12.5 per cent interest in Barossa.

Completion of the sell-downs to SK E&S and JERA will see Santos’ interests in Bayu-Undan and Darwin LNG change to 43.4 per cent, and in the Barossa project to 50 per cent.

The Barossa investment decision will see approximately 380 million barrels of oil equivalent resources commercialised to 2P reserves at Santos’ expected 50 per cent interest in the project following the sell-down to JERA.

About Santos

An Australian energy pioneer since 1954, Santos is a leading oil and gas producer, supplying Australian and Asian customers.
With over 3,000 employees across Australia and Asia, Santos’ foundations are based on safe, sustainable operations and working in partnership with host communities, governments, business partners and shareholders.


Origine : Communiqué Santos

Voir la fiche entreprise de "Santos"



Les dernières news de "Santos"



Toutes les news de "Santos"
 
 
Emploi-Pétrole
 
Rechercher une news



française internationale








 
Les dernières news internationales


>> Toute l'actualité internationale     >> RSS
 



Europétrole © 2003 - 2024