  • McDermott to Install Umbilicals & Subsea Equipment in Deepwater Gulf of Mexico Walker Ridge Field Development
    édité le 01/07/2013 - Plus de news de "McDermott" - Voir la fiche entreprise de "McDermott"


McDermott to Install Umbilicals & Subsea Equipment in Deepwater Gulf of Mexico Walker Ridge Field Development
McDermott International, Inc. announced that one of its subsidiaries has been awarded an engineering, procurement and construction (EPC) contract by Exxon Mobil Corporation for its Julia development. The value of the contract is included in McDermott's second quarter 2013 backlog.

The Julia field is located approximately 265 miles southwest of New Orleans in the Gulf of Mexico Walker Ridge area in water depths of approximately 7,000 feet. The Julia Phase I project is a subsea tie-back to a semi-submersible floating production unit and the scope includes six subsea wells, one six-slot manifold, two umbilicals, six jumpers, two flowlines with two steel catenary risers, two subsea pump modules and topsides support equipment. Production will flow through two 10-inch production flowlines with subsea single-phase boost pumps. Exxon Mobil Corporation, the operator, and Statoil each hold a 50 percent interest in the Julia field development.

“McDermott offered a very competitive solution for the Julia project with the right people, assets and technology, based on our experience with a similar deepwater Gulf of Mexico subsea tie-back project that we were awarded in 2011,” said Stephen M. Johnson, Chairman, President and Chief Executive Officer of McDermott. “The Julia subsea infrastructure requires a high level of engineering design and construction work, a key component of which is high-specification welding to help ensure long-term integrity and reliability of the subsea facilities. The installation solution we offer provides a high degree of reliability and precision using key vessels in our fleet for deepwater lowering and flexible lay, and further demonstrates our commitment to the subsea market.”

McDermott will undertake engineering, procurement and construction of the jumpers, four suction piles associated with the manifold, subsea pump, pump transformer and Subsea Distribution Unit /Umbilical Termination Assembly, as well as the transportation and installation of the manifold, suction piles, flying leads, subsea pump system, the power and control umbilicals and SDU/UTAs. McDermott will also carry out testing of the tie-back system and mechanical completion before hand over to the customer.

McDermott expects to successfully execute this high‐profile project employing its in‐house expertise and capabilities for subsea engineering, high‐spec fabrication and subsea installation. Work will commence with immediate effect in our Houston office.

McDermott deepwater installation vessel Derrick Barge 50 is expected to undertake the installation of suction piles and subsea equipment, including the manifold, pump station and transformer. The vessel’s new deepwater lowering system has the capability to lower loads of up to 480 tons to depths of up to 11,500 feet.

In addition, North Ocean 102 (NO102) is scheduled to transport and install umbilicals, flying leads and jumpers. NO102 is a fast-transit vessel with horizontal carousel. Recent improvements include installation of a high-capacity flexible-lay system to enable ultra deepwater installation work – comprising a 330-ton top-tension flex-lay tower, with 275-ton active heave compensation crane and 330-ton hang-off clamp capable of lowering loads to a depth of 10,000 feet.

The offshore installation campaign is expected to begin second quarter of 2015 and extend through 2015.

About McDermott
McDermott is a leading engineering, procurement, construction and installation group of companies focused on executing complex offshore oil and gas projects worldwide. Providing fully integrated EPCI services for upstream field developments, the Company delivers fixed and floating production facilities, pipelines and subsea systems from concept to commissioning. McDermott’s customers include national and major energy companies. Operating in more than 20 countries across the Atlantic, Middle East and Asia Pacific, our integrated resources include approximately 14,000 employees and a diversified fleet of marine vessels, fabrication facilities and engineering offices. McDermott has served the energy industry since 1923.


Origine : Communiqué McDermott

Voir la fiche entreprise de "McDermott"



Les dernières news de "McDermott"



Toutes les news de "McDermott"
 
 
 
Emploi-Pétrole
 
Rechercher une news



française internationale








 
Les dernières news internationales


>> Toute l'actualité internationale     >> RSS
 



Europétrole © 2003 - 2024