Key milestone for the H2med corridor: BarMar maritime pipeline project moves into the detailed engineering phase (FEED)
édité le 22/07/2026 - Plus de news de "Enagás" - Voir la fiche entreprise de "Enagás"

The H2med consortium announces a major milestone in the development of the European Union’s first major green hydrogen corridor. Following the successful completion of pre-engineering studies (pre-FEED), the BarMar offshore project, which will connect Barcelona and Marseille, is officially entering its Front-End Engineering Design phase (FEED). This move into detailed engineering marks the start of a crucial stage in confirming the technical viability and final design of this international-scale subsea infrastructure.
From feasibility to detailed design
The completion of the BarMar pre-FEED phase confirmed the project’s overall technical feasibility, as well as the design basis for the compression station and pipeline. An advanced corridor route has also been defined, drawing on the initial findings of the environmental impact assessment, which is still ongoing.
Moving into the FEED phase represents a critical transition from conceptual design to the project’s final technical architecture. This phase will draw on inputs from environmental and technical studies, as well as feedback received through the public consultation process in France and Spain, which concluded in July 2026. In France, the concertation guarantors will publish a feedback report including recommendations, which will be taken into account by the project promoters.
The FEED phase will specifically support the following activities:
- confirming the pipeline design and final route;
- finalising the compression station layout;
- preparing the permitting files;
defining the technical specifications required for construction preparation and material procurement.
- Next step will be awarding the FEED engineering design and offshore detailed marine survey. The FEED studies will also provide the technical basis needed by partners and investors to make the Final Investment Decision (FID) of BarMar before construction begins, with the commercial operation date in 2032.
Under the funding allocated in January 2025 to the H2med corridor projects by the European Commission under the Connecting Europe Facility (CEF), the H2med-BarMar project benefited over € 28 million, notably enabling the partners to finance these engineering studies, along investments by the promoters. This includes marine and environmental survey campaigns, as well as all necessary works for environmental impact assessments and securing required permits.
“We are moving from feasibility studies to concrete industrial modelling, a key step towards supporting Europe’s decarbonisation objectives. Designated as a Project of Common Interest (PCI) and Energy Highway by the European Commission, H2med aims for commissioning by 2032, provided that all regulatory conditions are met across the H2med corridor”, stated BarMar CEO Francisco de la Flor.
A strong political momentum for the H2med corridor
Alongside these technical milestones, a ministerial meeting under the High-Level Group on South-West Europe was held on 6th July in Paris, bringing together Energy ministers from Portugal, France and Spain, European Energy Commissioner Dan Jørgensen, regulators and operators to strengthen cooperation and align on the strategic rollout of the energy interconnections. This high-level representation, also in presence of Germany for the first time in this regional group, exemplifies the strong political momentum for European interconnections, amongst which the H2med corridor.
About ENAGÁS
Enagás is a Transmission System Operator (TSO) with 50 years’ experience in the development, operation and maintenance of energy infrastructure. The company has approximately 12,000 kilometres of gas pipelines, three underground storage facilities and eight regasification plants. The company operates in seven countries. In Spain, it is the Technical Manager of the Gas System and has been appointed Interim Manager of the Hydrogen Transmission Network (HTNO) by Royal Decree Law 8/2023. By agreement with the Council of Ministers, Enagás has been entrusted with the development of H2med, the Spanish hydrogen network and associated storage facilities. In line with its commitment to energy transition, Enagás has announced its target of becoming carbon neutral by 2040, with a firm commitment to decarbonisation and the promotion of renewable gases, especially hydrogen.
Origine : Communiqué Enagás
| Les dernières news de "Enagás" |
- 22/07/2026 - Key milestone for the H2med corridor: BarMar maritime pipeline project moves into the detailed engineering phase (FEED)
- 21/04/2026 - Enagás reaches an agreement to acquire 31.5% of the French operator Teréga and closes the sale of 40% of Enagás Renovable
- 16/04/2026 - European industrial leaders join forces to accelerate clean hydrogen deployment for industrial competitiveness and energy independence in Europe
- 19/01/2026 - Naturgy and Enagás to charter an LNG supply vessel that will become a European benchmark in the decarbonisation of maritime transport
- 06/01/2026 - Transported natural gas demand has grown by 7.4% in 2025 in the Spanish Gas System to 372 TWh
- 10/11/2025 - The Musel Energy Hub terminal in the Port of Gijón, ready to supply BioLNG to ships and tankers
- 27/06/2025 - Solvay and Enagás join forces to develop a strategic hydrogen storage in Spain
- 24/02/2025 - Enagás terminals in Barcelona and Huelva, ready to supply BioLNG to ships and tankers
- 11/02/2025 - Results of the Call for Interest - H2med promoters share insights and outline future steps of the project
- 03/01/2025 - Enagás : In 2024, demand for natural gas reached 311.7 TWh in Spain
- 26/11/2024 - World first: Veolia, Enagás and Barcelona City Council inaugurate the first sustainable urban cold recovery network at an LNG terminal
- 08/11/2024 - H2med project is launching its Call for Interest
- 09/10/2024 - Enagás and Gasunie sign an agreement to develop decarbonization projects and value chains
- 31/07/2024 - The Government authorises Enagás to start work on H2Med, the Spanish hydrogen network and associated storage facilities
- 28/05/2024 - Enagás leads the decarbonisation of maritime transport and quadruples LNG supply to ships in two years
- 13/12/2023 - Successful completion of the adaptation of the Sagunto Terminal to supply LNG to ships
- 30/11/2023 - H2med and the Spanish Hydrogen Backbone, included in the list of Projects of Common Interest of the European Commission
- 27/09/2023 - Enagás enters Germany with the closing of the Hanseatic Energy Hub (HEH) operation
- 14/08/2023 - El Musel LNG Terminal receives its first commercial ship
- 03/07/2023 - Enagás : El Musel terminal receives first LNG ship
- 09/06/2023 - El Musel LNG terminal receives Administrative Authorisation for its start-up
- 06/06/2023 - Enagás begins the binding phase of the assigning logistics services process at El Musel
- 02/06/2023 - Enagás becomes industrial partner and co-shareholder of Hanseatic Energy Hub in Stade
- 02/05/2023 - Spain reaches an all-time record of natural gas exports to France via the Pyrenees
- 25/04/2023 - Enagás advances in the fulfilment of its Strategic Plan and obtains results as planned
- 07/03/2023 - European TSOs Enagás, GRTgaz, REN and Teréga signed an agreement to boost transformation of the gas grid into hydrogen grid
- 03/03/2023 - Enagás begins the process of assigning logistics services at El Musel terminal
- 01/03/2023 - Enagás has acquired the Reganosa network of natural gas pipelines, which will enter into the shareholding of El Musel Regasification Plant with 25%
- 16/01/2023 - Enagás agrees to join European interconnector BBL
- 16/12/2022 - Saggas loads the first vessel to operate as a floating regasification plant in Germany
- 15/12/2022 - Enagás, GRTgaz, Teréga and REN sign an MoU for the development of H2MED
- 29/10/2022 - From Tuesday November 1st, the capacity expansion of the Irún interconnection will be available to increase flows from Spain to France
- 05/10/2022 - Enagás signs an agreement with the Albanian operator AlbGaz for potential acquisition of a stake in the company and to engage in joint projects
- 19/08/2022 - Enagás a commencé le processus de sélection du personnel pour travailler au terminal El Musel de Gijón
- 25/07/2022 - Enagás and OMERS Infrastructure close the joint sale of their stakes in Chilean company GNL Quintero
- 13/07/2022 - Enagás will invest 2,775 million euros in security of supply and decarbonisation up to 2030
- 28/03/2022 - Enagás and OMERS Infrastructure agree to sell their stakes in Chilean company GNL Quintero
- 27/10/2021 - Enagás, Edison and PIR inaugurate continental Italy’s first small scale LNG terminal for sustainable in the transport sector
- 19/03/2021 - Work progresses on the first LNG supply vessel built in Spain
- 22/12/2020 - The European Commission supports the construction of the first LNG bunkering vessel to operate at the Port of Algeciras
- 03/08/2020 - The European Commission supports new projects to supply LNG to ships in Spanish ports
- 06/07/2020 - Enagás and bp are teaming up to promote emission reduction in Spain
- 25/04/2019 - The ports taking part in the CORE LNGas hive project are ready to supply ships with liquefied natural gas (LNG)
- 10/12/2018 - First pilot test of LNG transport by road, rail and sea successfully carried out in Europe
- 23/11/2018 - Enagas closes the sale of its stake in Swedegas
- 15/11/2018 - The European Commission selects the initiative LNGHIVE2, coordinated by Enagas, to boost LNG as an alternative fuel
- 18/09/2018 - Enagas and Reganosa are jointly participating in the tender for the operation of an LNG terminal in Kuwait
- 03/09/2018 - Enagas and Fluxys agree the sale of the Swedish transmission system operator Swedegas
- 20/07/2018 - The Snam, Enagas, Fluxys consortium signs the agreements for the acquisition of 66% of the greek operator DESFA
- 12/07/2018 - Enagas signs guiding principles for reducing methane emissions
|
Toutes les news de "Enagás" |
|

|