Cheniere Energy Partners, L.P. (Cheniere Partners) , a subsidiary of Cheniere Energy, Inc. (Cheniere), announcedthat certain of its subsidiaries have initiated the pre-filing review process under the National Environmental Policy Act with the Federal Energy Regulatory Commission (“FERC”) for the proposed Sabine Pass Stage 5 Expansion Project (the “SPL Expansion Project”) adjacent to the existing Sabine Pass Liquefaction Project (the “SPL Project”). The SPL Expansion Project is being designed for total production capacity of approximately 20 million tonnes per annum (“mtpa”) of liquefied natural gas (“LNG”).
The SPL Expansion Project is being designed to include up to three large-scale liquefaction trains, each with a production capacity of approximately 6.5 mtpa of LNG, a boil-off-gas (“BOG”) re-liquefaction unit with an approximate production capacity of 0.75 mtpa of LNG, and two 220,000m3 LNG storage tanks. The SPL Expansion Project is being designed with accommodations for waste heat recovery as well as carbon capture from acid gas removal units.
The SPL Expansion Project is expected to benefit from the significant existing infrastructure at the SPL Project and contemplates various enhancements to its current capabilities, including optimized ship loading at the existing marine facilities. Feed gas related to the SPL Expansion Project is expected to be transported via a combination of new and existing pipelines currently supplying the SPL Project.
Cheniere Partners has engaged Bechtel Energy, Inc. to complete a Front-End Engineering and Design (FEED) study of the SPL Expansion Project.
“As the first and largest LNG export facility in the Lower 48, Sabine Pass has pioneered an industry critical to supplying reliable, flexible, and cleaner burning natural gas to markets and customers around the world, and we look forward to significantly growing those capabilities through the SPL Expansion Project,” said Jack Fusco, Chairman, President and CEO of Cheniere Partners. “The SPL Expansion Project is being designed to leverage the infrastructure platform we’ve built at Sabine Pass to deliver economically advantaged incremental LNG capacity in a safe and environmentally responsible manner. We are committed to developing the SPL Expansion Project utilizing the same rigorous and financially disciplined approach to project development and capital investment that’s become synonymous with the Cheniere brand.”
The development of the SPL Expansion Project, and any necessary supporting infrastructure, is subject to receipt of all required regulatory approvals and permits, and sufficient commercial and financing arrangements before a final investment decision (“FID”) can be reached.
About Cheniere Partners
Cheniere Partners (NYSE American: CQP) owns the Sabine Pass LNG terminal located in Cameron Parish, Louisiana, which has natural gas liquefaction facilities consisting of six liquefaction Trains with a total production capacity of approximately 30 million tonnes per annum of liquefied natural gas. The Sabine Pass LNG terminal also has operational regasification facilities that include five LNG storage tanks, vaporizers, and three marine berths. Cheniere Partners also owns the Creole Trail Pipeline, which interconnects the Sabine Pass LNG terminal with a number of large interstate and intrastate pipelines.